Projects
Rangwee Tunnel II
Category
Box Sliding Operation
As a result of the development of the multimodal hub in Howald and the redevelopment of Rue des Scillas, traffic into Luxembourg will increase at the Glück roundabout. Félix Giorgetti built a second tunnel alongside the Rangwee tunnel.
This project involves building a second tunnel to connect the Glück roundabout to Rue des Scillas, south of the Luxembourg capital. Rangwee II is composed of two 2,500-ton frames, each 30m long, 13m wide and 7m high.
The structures were built side by side, at the foot of the embankment supporting the CFL railway tracks.
Each element was positioned in just two weeks using the box jacking process. The operation required blocking the CFL tracks and setting up continuous work in three shifts.
36h
Sliding of two frames
2,500t
Weight per frame
30 x 13 x 7m
Frame dimensions
12,000m3
Earthworks
Works carried out
Extensive preparatory work
A lot of work was carried out before reaching this stage. This included:
- The excavation of a huge pit used to site-cast the elements;
- Building soldier pile walls to shore up the site-casting pit;
- The construction of a 1,300m2 guide slab with a very rigorous flatness, less than 3mm of play, which was necessary to push the elements forward;
- Casting the slab and the walls of the prefabricated frames;
- Building the formwork for the slab of the frames, using a shoring tower for the whole process;
- Concreting the slab of the prefabricated frames;
- Waterproofing the slabs;
- Site-casting concrete thrust blocks so that the two frames could be jacked.
Race against time
An actual race against time began from the moment the overhead lines were deactivated. 36 hours during which our teams relayed each other continuously in three shifts. 12,000m3 of earth were excavated in order to open the way for the frames before preparing the guide slab and starting to thrust the frames using jacks.
This delicate operation took place in two stages. It began by thrusting the first element: raised by about 5cm and already in line, it reached its final location. The second frame was first pushed laterally so that it would be positioned along the right axis and then thrust forward until it was next to the first frame.
Once this stage was completed, it was necessary to backfill all around the tunnel in order to recreate the embankment and proceed with laying the tracks and signals for CFL.
The project also involved building a stormwater tank next to the new tunnel. Due to the lack of space, the structure was built at the foot of the CFL tracks using considerable shoring and a 14m deep pit.
Projets similaires
Redesign of the Pontpierre interchange
2023
Redevelopment of the Pontpierre interchange on the A4 to improve traffic flow and safety for local residents.
Dippach-Gare bypass
2023
Construction of a 2.2 km bypass to relieve traffic congestion on the rue des Trois Cantons.
Hosingen cut-and-cover tunnel
2023
The cut-and-cover tunnel is the first section of the Hosingen bypass.
Glaasbuurgronn and Groussheck viaducts
1998
As part of the construction of the Route du Nord, Félix Giorgetti carried out numerous works including the construction of two viaducts, Glaasbuurgronn and Groussheck.