Projects
CFL multimodal warehouse
Category
A 30,000m2 warehouse for CFL Multimodal
As part of the construction of the multimodal terminal, CFL has entrusted Félix Giorgetti with the construction of a 30,000 m2 logistics hall.
This new tool has allowed CFL Multimodal to bring together all its logistics activities, taking advantage of the site's strategic location, in direct proximity to the international highway network, the intermodal terminal, the rail highway platform and the marshalling yard.
30,000m2
Bulding's surface
20m
Ridge height
400m2
Office's area
Very good
BREEAL certification
It also includes 400m2 of office space. In addition to the 13,000 pallets that can be stored in height, the building can accommodate 12,000 rolls, 50,000 tires, 1,500 pallets kept at +5°C or 450 pallets at -23°C.
The works required 100,000 t of 0/50 HF platform fill, 13,000m3 of cast-in-place concrete, 3,200m3 of prefabricated structure (columns and beams), 870m3 of prefabricated firewalls and 6,300m of prefabricated slabs in hourdis.
Our client
Project owner
CFL
Key figures
Storage of pallets in height
13,000
Loading docks
64
Backfill platform in 0/50 HF
100,000t
Cast-in-place concrete
13,000m3
Prefabricated structure columns and beams
3,200m3
Prefabricated firewalls
870m3
Prefabricated slabs in hourdis
6,300m
Projets similaires
Redesign of the Pontpierre interchange
2023
Redevelopment of the Pontpierre interchange on the A4 to improve traffic flow and safety for local residents.
Dippach-Gare bypass
2023
Construction of a 2.2 km bypass to relieve traffic congestion on the rue des Trois Cantons.
Hosingen cut-and-cover tunnel
2023
The cut-and-cover tunnel is the first section of the Hosingen bypass.
Glaasbuurgronn and Groussheck viaducts
1998
As part of the construction of the Route du Nord, Félix Giorgetti carried out numerous works including the construction of two viaducts, Glaasbuurgronn and Groussheck.